| Planning Permit / NZS location definition |
Condition 23(a) requires wind farm sound levels to be determined in accordance with NZS 6808:2010 at noise sensitive locations “as defined in the Standard”. The NZS definition includes any point within the notional boundary of relevant buildings; the Standard separately defines the notional boundary as 20 metres from the dwelling or other building used for a noise sensitive activity, or the legal boundary where this is closer. |
Planning Permit Condition 23(a); NZS 6808:2010 |
| NZS definition | Background sound is addressed by reference to the A-frequency-weighted L90 centile level measured before wind turbines are installed in an area. The Standard is used as source material only and is not reproduced on this website. | NZS 6808:2010; Annex A; Verification Schedule |
| NZS definition – Notional boundary | A notional boundary is described as a line 20 metres from any side of a dwelling or other building used for a noise sensitive activity, or the legal boundary where this is closer to such a building. The Standard is used as source material only and is not reproduced on this website. | NZS 6808:2010; NCTP; Annex A; Verification Schedule |
| October–December 2017 second survey | The monitor was relocated to the front / eastern side of the dwelling, identified as the only alternative position in accordance with NZS 6808:2010. The second-survey data was still recorded as affected by local sources and not suitable for deriving noise limits or assessing post-construction compliance. | Marshall Day Background Noise Monitoring Report; Annex A |
| NCTP pre-operation requirement | The NCTP recorded that, before commencement of operation, an updated background noise report was to be submitted to the Responsible Authority detailing the K15aa monitoring results. | NCTP; Annex A; Verification Schedule |
| 1 December 2022 SLR letter | SLR recorded the operator's position that pre-construction baseline monitoring at K15aa was completed in approximately October 2018. This is recorded in the record as part of the K15aa chronology for the southern receiver group. | SLR Elaine Wind Farm – Noise Compliance letter; Annex A |
| October 2024 operator correspondence | The Beneficiary identified the February 2021 SLR K15aa Baseline Noise Monitoring Report and asked the operator to verify the updated background report submitted to the Responsible Authority before operation. The operator had stated that all reports required under the planning permit were submitted to the relevant authority. | Operator correspondence, 14–15 October 2024; NCTP; DTP FOI CS015467 |
| DTP custody | DTP is the Responsible Authority for the permit noise compliance framework. In FOI CS015467, DTP advised it did not locate documents recording submission of the February 2021 SLR baseline report and stated that baseline studies are typically background input material not generally provided to the Department. | DTP FOI CS015467; Annex D; SRAM |
| DTP Part 4 enquiries | DTP's supplementary clarification dated 4 August 2026 records that, following relevant enquiries, the Department was unable to locate any documents in response to Part 4 of FOI CS019200. Part 4 sought documentary authority for identified departures from the NZS 6808:2010 definitions of background sound level and notional boundary. | DTP FOI CS019200 decision and supplementary clarification |
| EPA FOI custody | The EPA FOI-100-2025 request also sought documentary material relating to the K15aa background sound record. The Notice of Decision does not identify a decision or released document specifically addressing that component of the request. The record records this as part of the documentary custody pathway for K15aa. | EPA FOI-100-2025 Notice of Decision; Annex A; Annex D |