Documentary timeline

Chronology

This chronology places the governing framework, technical assessments, commissioning material, regulatory disclosures and Trustee administrative record in date order. Its purpose is to show how the documentary pathway developed and where later material must be read against earlier requirements.

Reading position: The chronology records what particular documents say and when they arose. Where records use different dates or describe different operational milestones, the difference is preserved rather than resolved by assumption.
Purpose

Why chronology matters

A technical or regulatory document cannot be understood only by its publication date. The relevant sequence may include the date of the governing requirement, the monitoring period, construction or energisation, commissioning, report preparation, auditor review, regulatory reliance and later disclosure.

1

Requirement date

Identify when the governing permit condition, standard or endorsed methodology became part of the applicable documentary framework.

2

Event and evidence date

Distinguish the date of monitoring, construction, energisation, commissioning or assessment from the later date on which a report was issued.

3

Reliance and disclosure date

Identify when an auditor or agency referred to, relied upon, released or stated that it could not locate particular material.

How to read this page

Dates are attributed to their source

The chronology is a documentary navigation tool, not a substitute for the source documents. It separates established dates from dates reported by particular parties and identifies conflicting or incomplete chronology where the available record does not establish one reconciled position.

What an entry establishes

An entry establishes that the identified document, event, statement or disclosure appears in the available record at the stated date. It does not give every document the same authority or convert a later statement into an amendment of an earlier requirement.

What a difference in dates means

Different dates may refer to construction completion, first energisation, generation, individual turbine commissioning, final turbine commissioning, commencement of operation or administrative closure. The chronology preserves those distinctions unless a source expressly reconciles them.

Documentary hierarchy

The record developed in layers

The sequence begins with the legal and planning framework, continues through the endorsed technical method and assessment record, and then moves to auditor material, agency reliance, Freedom of Information disclosure and the continuing administrative record.

Principal chronology

Governing, technical and administrative record

Each entry identifies the event or document, its documentary significance and the page or source material through which it can be examined further.

Period / dateRecord eventDocumentary significanceRead next
Planning frameworkPlanning Permit PL-SP/05/0461 and operational noise conditionsThe permit establishes the project permission and the operational noise pathway. Conditions 23–25 connect the permit to the applicable standard, compliance assessment and endorsed testing plan.Framework
2017Original background monitoring and preparation of the NCTPThe original monitoring record supplied background information used in the technical pathway and identified K15aa for updated background monitoring before operation.K15aa
23 January 2018Noise Compliance Testing Plan, MDA 003 R03The endorsed NCTP records the compliance monitoring and reporting pathway, including the requirement for an updated K15aa background noise report before commencement of operation.NCTP
June 2018Sonus Pre-construction Noise Assessment S5464C11A later predictive assessment for the proposed turbine layout. Its documentary role is distinct from the formal Marshall Day pre-construction assessment and later Environmental Auditor verification pathway.Sonus 2018
2019Supplementary K15aa background monitoringThe monitoring later reported by SLR forms the updated K15aa baseline record. Its timing must be read with the construction, energisation, generation and commissioning chronology.K15aa
1 October 2019Community Reference Group recordThe public meeting record states that construction was complete while commissioning was continuing, providing contemporaneous context for the transition between construction and operation.Start Here
October–November 2019Energisation and generation recordsSLR Appendix H records turbine energisation and generation during this period. Those records are relevant when assessing whether monitoring described as background monitoring occurred before turbine installation or operation in the area.Appendix H
18–19 November 2019 / recorded in 2019–2020 public materialFinal-turbine commissioning milestone implied by landscaping chronologyThe Community Reference Group minutes dated 4 December 2019 state that the landscaping program would close 12 months after commissioning of the last turbine and identify 18 November 2020 as the closure date, implying commissioning on 18 November 2019. The June 2020 Community Bulletin states that the program would remain open until 19 November 2020, implying 19 November 2019. The source-specific one-day difference is preserved.Commissioning gateway
10 December 2020Operator commissioning date later reported in the agency recordAn IGN response states that the last turbine was commissioned and the wind farm commenced operating on this date. Other records use later commissioning-related dates, so this date is attributed to that source rather than treated as the only chronology.Agency records
16 February 2021SLR K15aa Compliance Baseline Noise Monitoring Report, v1.1The report publishes the supplementary K15aa assessment based on monitoring undertaken in 2019. The report date follows the 10 December 2020 operational date identified in the later agency response.K15aa
9 March–13 May 2021Elaine Stage 1 post-construction monitoringThe monitoring period later documented in the Elaine Stage 1 assessment. Its timing is relevant to the NCTP and NZS post-construction assessment windows.Technical reports
Mid-2021 / July 2021Later commissioning-related recordsA VCAT statement refers to the last turbine being commissioned in mid-2021, while Council landscaping closure material used July 2021 as the relevant twelve-month milestone. These records are not treated as silently overriding the different date reported elsewhere.Verification
June 2022Environmental Auditor verification-document chronologyThe available record uses different descriptions, including “Verification Audit” and “Draft Verification Report”, within closely dated material. The distinction is preserved as part of the verification record.Verification
June–August 2022Yendon Stage 1 post-construction monitoringThe monitoring period later recorded in the final Yendon Stage 1 report.Technical reports
27 June 2022SLR Elaine Stage 1 Post-construction Noise Assessment, v1.7An earlier Elaine Stage 1 report recording the methodology and results of monitoring undertaken during March–May 2021. It later appeared within EPA correspondence.Report · EPA email
18 October 2022Noise Management Plan, Version 3.0The available document is marked Final Revision 03. Later EPA material refers to continuing revision, auditor review and draft status, creating a separate documentary chronology examined on the NMP page.NMP
21 October 2022ARUP correspondence concerning NZS 6808:2010The Auditor correspondence addresses technical verification issues and the distinction between mandatory and advisory wording within the standard.Technical reports
March 2023–January 2024Stage 2 monitoring, Elaine and YendonThe combined Stage 2 campaign was later documented in the September 2024 report. The monitoring period is separate from the date of report publication and verification.Technical reports
31 October 2023Final Elaine and Yendon Stage 1 reportsThe final published Elaine Stage 1 report is SLR 640.11872-R04 v2.0. The final Yendon Stage 1 report is SLR 640.11872-R15 v1.7.Technical reports
13 November 2023ARUP Elaine Stage 1 verificationEnvironmental Auditor verification of the final Elaine Stage 1 assessment.Documents
7 December 2023ARUP Yendon Stage 1 verificationEnvironmental Auditor verification of the final Yendon Stage 1 assessment.Documents
31 January 2024EPA documentary reliance recordEPA identified a collection of reports and plans used in its compliance assessment, including Sonus S5464C11 and the available Noise Management Plan.Agency records
20 September 2024SLR Stage 2 Post-construction Noise Assessment, revision 1.2The combined Elaine and Yendon Stage 2 assessment includes later technical review material and Appendix H.Technical reports
24 September 2024ARUP Stage 2 verificationEnvironmental Auditor verification of the Stage 2 assessment.Documents
4–7 October 2024Beneficiary enquiry concerning final turbine commissioning datesThe Beneficiary asked what authority required notification of individual turbine commissioning dates or requested the final commissioning dates for the Yendon and Elaine sections. The operator stated that its notifications and reports were completed in accordance with planning requirements and that it was not obliged to provide the requested information.Operational correspondence
2024–2025Beneficiary Freedom of Information recordEPA, Council and DTP decisions and correspondence contributed to the historical disclosure, search and document-custody record.FOI register
12 January 2026Notice of Systemic Procedural Non-Compliance and Interim Curtailment ProposalThe continuing administrative record formally placed the identified documentary issues and proposed interim response before relevant recipients.Administrative record
19 February 2026Statement of Matters of Public InterestThe Trustee’s public-interest record was placed before the Victorian Ombudsman with supporting annexures.Administrative record
30 March 2026 / 25 June 2026EPA FOI-010-2026 decision and later document releaseThe decision and later release added further agency, auditor and consultant material to the disclosed record. The decision date and actual release date are preserved separately.FOI register
15 April 2026Council FOI SR.142870 — commissioning recordsMoorabool Shire Council recorded searches for formal commissioning certificates, written notifications, milestone registers and internal records, and issued a no-documents-found decision.Decision
22 April 2026Governance — Administrative Record ClarificationThe Trustee recorded why the commissioning milestone matters to the documentary chronology and requested confirmation of Council's administrative position without alleging wrongdoing.Clarification
29 June 2026Notice — Crystallisation of Administrative and Regulatory RecordThe Trustee recorded completion of the then-current phase of documentary development while preserving the continuing nature of the administrative record.Record status
30 June 2026Crystallised record provided to the operator’s legal representativesThe completed package was transmitted as part of the continuing administrative and evidentiary record.Administrative record
6 July 2026Supplementary Public Interest Submission to the Victorian OmbudsmanThe crystallised record, including the SRAM versions, annexures, verification schedule, Trustee minutes, chronology and supporting material, was lodged for inclusion with the existing public-interest file.Documents
July 2026Public Lal Lal Wind Farm Record and agency gatewayThe public record was organised around the central documentary question, common terminology, governing framework, issue methodology, chronology, technical evidence and agency records.Agency records
16 July 2026EPA regulatory-position reconciliation noticeThe Trustee requested identification of the documentary pathway by which EPA reconciles its current regulatory position with the governing statutory and planning framework concerning K15aa.Focused entry
17 July 2026DTP FOI CS019200 decision and Trustee clarificationDTP recorded eight documents located and specified commissioning and completion records not located. The Trustee then sought clarification of the applicant identity and the determination of Part 4.FOI pathway
4 August 2026DTP FOI CS019200 supplementary clarification — Part 4DTP stated that, following relevant enquiries, it was unable to locate any documents in response to Part 4 concerning documentary authority for the identified departures from the NZS 6808:2010 definitions of background sound level and notional boundary. The outcome is recorded as a statutory disclosure result and is not treated as determining whether an authority existed elsewhere or the legal consequences of the disclosed record.FOI pathway
26 July 2026Professional clarification Notice issued to SLR Technical DirectorThe Trustee afforded a procedural-fairness opportunity to clarify professional positions and identify any documentary or authorising basis not apparent within the record.Operational Correspondence
2 August 2026Beneficiary advises Trustee of Australian Acoustical Society complaintThe Beneficiary advised the Trustee, for information and administrative-record purposes only, that a separate professional-conduct complaint had been lodged with the Australian Acoustical Society.Operational Correspondence
3 August 2026Professional clarification response period concludesThe response date stated in the 26 July Notice passed. The Notice had allowed a request for additional time if reasonably required.Operational Correspondence
8 August 2026No response to 26 July professional clarification Notice recordedAs at 8 August 2026, the Trustee records no response, acknowledgement or request for additional time. No adverse inference is drawn merely from the absence of a response.Operational Correspondence
29 July 2026Additional SAC material forwarded to SLRThe Trustee advised that the public SAC record had been expanded and provided the material for information and convenience only, expressly stating that the 26 July Notice remained unchanged.Operational Correspondence
5 August 2026DTP clarification forwarded to SLRThe Trustee forwarded DTP's 4 August clarification to Mr Reuterswärd and Mr Gardiner for information so that any response could be made against the current documentary record. The Notice remained unchanged.Operational Correspondence
7 October 2024 Beneficiary raises asserted third Elaine meteorological monitoring facility with Council The Beneficiary wrote to Council's Executive Manager Community Planning & Development concerning the permit allowance for meteorological monitoring facilities and requested the planning permit, authorising document or other instrument relied upon for what he described as a third Elaine meteorological monitoring facility and its relocation. Agency Records
8 April 2026 Moorabool Council FOI SR.139279 — Elaine meteorological monitoring facility Council recorded that its refined FOI search for any formal approval, consent, authorisation or endorsement relating to establishment or operation of the Elaine Meteorological Monitoring Facility identified no documents meeting the terms of the request. Permit Amendment
12 February 2025Elaine meteorological mast — observed removalThe Beneficiary emailed Council while the asserted third Elaine meteorological mast was being removed, recording that it was “currently being pulled down, today”.Agency Records
20-24 February 2025Council response and follow-up — Elaine meteorological mastCouncil said LLWF did not require a planning permit to remove the temporary mast. The Beneficiary then sought the separate secondary-consent or planning basis for its earlier presence and duration.Agency Records
Current documentary position: The available chronology identifies more than one commissioning-related date and distinguishes monitoring dates, report dates, verification dates, reliance dates and disclosure dates. No date is harmonised merely because a later document uses different terminology.
Focused chronology

Sonus S5464C11 and later disclosure

This focused sequence distinguishes the June 2018 Sonus report from later references to it, the formal pre-construction assessment and verification pathway, and the documents located through Freedom of Information.

June 2018

Sonus S5464C11

Sonus issues the later Pre-construction Noise Assessment for the proposed turbine layout.

2022

Later SLR and ARUP correspondence

Separate letters refer to Sonus predictions for J14aa, K15aa and the 35 dB(A) contour. Those references do not make the Sonus report the formal Marshall Day pre-construction assessment or its verification reports.

31 January 2024

EPA reliance record

EPA lists S5464C11 among the documents used in its compliance assessment.

FOI record

Report located; separate review not identified

DTP FOI CS015466 located and released the Sonus report. EPA FOI-031-2024 did not identify responsive auditor or peer-review documents for that request.

16 July 2026

EPA regulatory-position reconciliation notice issued

The Trustee issued the Notice — Documentary Reconciliation of EPA’s Current Regulatory Position to EPA Victoria’s Chief Executive Officer. The Notice requests identification of the documentary pathway by which EPA reconciles its current regulatory position with the governing statutory and planning framework concerning K15aa.

Focused chronology

Noise Management Plan documentary timeline

This sequence distinguishes the date and status shown on the available NMP from later EPA statements concerning auditor verification, continuing revision, draft status and regulatory reliance.

18 October 2022

NMP Version 3.0

The available document is marked Final Revision 03.

November 2023

Auditor verification requested

This request date was later identified by EPA in correspondence dated 21 June 2024.

31 January 2024

EPA reliance record

NMP 0467385 is listed among documents used by EPA to assess compliance.

22 May 2024

Revisions continuing

EPA states that revisions and Environmental Auditor review remained outstanding.

23 January 2025

Draft status recorded

EPA internal review states that EPA had seen a draft but not a completed final NMP.

4 February 2025

Draft dated October 2022

EPA confirms the date associated with the draft under discussion.

22 June 2026

DTP clarification sought

The Trustee placed the documentary chronology before the DTP permit-amendment enquiry contact.

Documentary enquiry

October 2024 K15aa report-submission enquiry

This entry records the operator's stated submission position and the Beneficiary's request to identify the updated K15aa background report required by the endorsed NCTP.

14 October 2024

Operator submission position

The operator stated that all reports required under the planning permit were submitted to the relevant authority in accordance with the planning conditions.

14–15 October 2024

Specific K15aa clarification sought

The Beneficiary identified the February 2021 SLR K15aa Baseline Noise Monitoring Report, referred to the NCTP requirement and asked the operator to verify the updated background report submitted to the Responsible Authority before operation.

Operational chronology

15 August 2024 complaint and on-site monitoring

This entry records the relationship between a contemporaneous operational complaint, SLR monitoring equipment operating at J14aa and the later operator response.

15 August 2024, early morning

Operational noise complaint

The Beneficiary reported being woken by turbine thumping and roaring, with the incident recorded as lasting more than two hours.

Approximately 3:34 am

SLR logger display recorded

A contemporaneous photograph and video record the on-site logger display at J14aa. The visible values include LAeq 47.8 dB, LAF90.0 45.6 dB, wind speed 1.2 m/s and wind direction 317°.

11 September 2024

Operator response

The operator's response recorded average wind speed of 9.5 m/s and average wind direction of 353.6°, and stated that wind conditions would not have caused excessive noise. The Beneficiary then asked whether the logger data had been reviewed during the investigation.

Evidentiary limits

What this chronology does not determine

The chronology does not make findings of compliance, non-compliance, causation, liability or regulatory validity. It does not infer that a missing document never existed, or that a disclosed document was the only material held or considered. It identifies the available sequence, attributes statements to their sources and directs readers to the underlying evidence.

Document date is not always event date

A report may be prepared months or years after the monitoring or event it describes. The chronology therefore preserves monitoring periods, issue dates, revision dates and disclosure dates separately.

Later reliance does not amend the framework

An agency’s later reliance upon a document records an administrative position. It does not by itself amend the planning permit, NZS 6808:2010 or the endorsed NCTP.

Focused chronology

2026 commissioning and DTP disclosure pathway

15 April 2026

Council FOI SR.142870 decision

Council recorded searches and that no responsive formal commissioning records were found within scope.

22 April 2026

Governance clarification issued

The Trustee requested confirmation of Council's administrative position concerning the commissioning milestone and associated post-construction chronology.

17 July 2026

DTP CS019200 decision and clarification request

DTP issued its access decision. The Trustee then requested administrative clarification concerning applicant identity and Part 4 of the request.

Focused chronology

DTP permit-amendment clarification pathway

This sequence records the Departmental reliance, amendment determination and later administrative clarification correspondence without determining the legal effect of the amended permit.

7 April 2026

Departmental reliance position recorded

The Trustee sought clarification as to whether the Department maintained its earlier reliance position after receiving the Supporting Record and Annex materials.

15 May 2026

Amendment determination issued

The Department issued the determination correspondence and final amended permit material.

18 May 2026

Administrative clarification and reconciliation Notice

The Trustee sought clarification concerning Transitional Condition 27A, responsible-authority wording, meteorological monitoring wording and the relationship between the exhibited amendment and final permit.

26 May 2026

Status enquiry

The Trustee sought only updated status information or an indicative timeframe.

26 June 2026

Administrative record position recorded

No acknowledgement or substantive response was recorded. The Trustee advised that it would proceed on the available administrative record while remaining open to later clarification.

12 July 2026

Public reference material provided

The Department was advised that the Permit Amendment and Noise Management Plan public-reference pages were available for information only.

Operational incident chronology

2026 — Y23 blade failure and later site condition

This sequence records the incident date, the earlier third-party footage and the later 27 August site record. It distinguishes visible site condition from any conclusion about pollution, contamination or regulatory compliance.

15 May 2026

Blade failure at turbine Y23

The operator recorded a blade failure at turbine Y23 at the Yendon Wind Farm at approximately 6:45 am.

23–24 May 2026

Earlier third-party footage and Trustee enquiry

Third-party footage supplied through the Beneficiary was incorporated into the administrative record. The Trustee subsequently sought clarification concerning debris recovery, dispersion, surrounding land and waterways, authority notification and community information.

15 June 2026

EPA identifies its clean-up role

EPA advised the Beneficiary that it was making enquiries into the broken wind farm blade and stated that its role was limited to ensuring appropriate disposal and clean-up following the incident. That response later formed the express basis of the Trustee's 27 August follow-up under ENQ231138.

29 May 2026

Earlier footage provided to EPA South West and Central Highlands Water

The Trustee provided the incident footage to EPA South West and Central Highlands Water for information, public-interest and record purposes. The correspondence identified debris containment and recovery, surrounding land, drainage lines and waterways, relevant authority notification and environmental or public-health assessment, while expressly making no allegation or finding concerning the incident.

27 August 2026 — 104 days later

Later site footage records substantial material still present

New third-party footage records substantial blade sections and dispersed smaller fragments remaining visible around the Y23 incident area. Compared with the earlier May footage, no material general clean-up of the dispersed debris is apparent from the later visual record. Available locality rainfall records indicate approximately 200 mm of rainfall during the intervening period, including approximately 42 mm on 10 August. A supplied map records Y23 approximately 2.5 km in a straight line from Lal Lal Reservoir.

The rainfall and reservoir-proximity information provide environmental context only. The record does not establish that blade material or contaminants entered a drainage line, waterway or reservoir.

External administrative oversight

August 2026 — Victorian Ombudsman complaint record

The chronology separates four distinct complaint pathways. Lodgement or closure correspondence is recorded as a procedural event and is not treated as an Ombudsman finding on the underlying allegations.

14 August 2026

Online Council complaint — C/26/15485

An online complaint was lodged concerning Moorabool Shire Council's failure to substantively respond to or adequately administer the Trustee's Condition 17 records enquiry. The underlying enquiry began on 13 July and was followed up on 23 July, 29 July and 10 August.

18 August 2026

EPA Victoria complaint lodged

The Trustee lodged a complaint concerning EPA's administrative and regulatory decision-making and its continuing compliance position in relation to Lal Lal Wind Farm.

18 August 2026

Separate Moorabool Shire Council complaint lodged

A substantively distinct complaint was lodged concerning Council's historical administration and investigation of Planning Permit PL-SP/05/0461, including its December 2022 no-breach determination. The complaint expressly distinguishes itself from C/26/15485.

24 August 2026

C/26/15485 — closure correspondence and clarification request

The Ombudsman advised that it would take no further action under C/26/15485, describing concerns about Council's 2022 permit-compliance assessment, technical advice and record gaps. The Trustee then sought clarification as to whether that assessment related to the 14 August online complaint, because the online complaint concerned the separate Condition 17 non-response pathway.

10–24 August 2026

DTP / Ministerial reconciliation opportunity

The Trustee gave the Minister for Planning a further opportunity to address the developed administrative record. A follow-up was sent on 18 August; the Trustee records that the 14-day period expired on 24 August without acknowledgement or substantive response addressing the matters raised.

25 August 2026

DTP complaint lodged

The Trustee lodged a formal complaint concerning DTP's administration of Planning Permit PL-SP/05/0461, the documentary foundation for its stated NZS 6808:2010 compliance position and the 2026 permit amendment.

Status: the public record presently establishes the complaint lodgements and the C/26/15485 correspondence described above. It does not record an Ombudsman finding on the EPA, substantive Council or DTP complaints.
August 2026 · professional standards

Professional standards and complaint pathways

The professional-body pathways are recorded separately from government and Ombudsman oversight. The public record preserves the independently existing professional correspondence and the capacity in which each pathway was invoked; the formal complaint documents themselves are not reproduced.

2 August 2026: the Beneficiary advised the Trustee that he had independently lodged an Australian Acoustical Society complaint concerning Mr Gustaf Reuterswärd in his private capacity.

13, 15 and 22 August 2026: the Trustee's separate AAAC external-complaint pathway records complaints concerning SLR Consulting Australia Pty Ltd, ARUP Australia Pty Ltd and Marshall Day Acoustics Pty Ltd. A separate Resonate Consultants pathway is also recorded on the dedicated page.

29 August 2026: the Beneficiary's separate AAS pathway concerning Mr Thomas Evans is recorded following completion of the Trustee's direct Resonate correspondence and provision of that material to the Beneficiary for information and independent consideration.

Capacity safeguard: Trustee correspondence supplied to the Beneficiary did not make the Trustee the complainant in the AAS process and did not direct, authorise or request the Beneficiary to complain.