Technical learning hub

Technical Reports

A guided pathway through the technical documents that underpin the Lal Lal Wind Farm administrative and evidentiary record.

Why chronology matters

Read reports in sequence

Technical reports do not exist independently of one another. Earlier reports establish assumptions, monitoring methods and baseline information that later reports may rely upon, verify or revisit. Understanding the order in which reports were prepared helps readers understand the documentary record.

Reading guide

Purpose of this page

This page helps readers understand how the technical record developed. It does not replace the source documents, the Glossary, or the evidence pages. It shows how the technical reports fit together before readers move into detailed issues such as K15aa, NCTP, NZS 6808 and SAC.

Pre-construction pathway

Pre-construction Acoustic Assessments

Follow the planning-stage acoustic record through Marshall Day background monitoring, the April 2018 Sonus prediction, AECOM Environmental Auditor peer review and the now-published June 2018 Sonus assessment S5464C11. The pathway also distinguishes later EPA, SLR and ARUP references from the formal PCNA and Environmental Auditor verification record, which identifies the Marshall Day/NCTP pathway.

Post-construction pathway

Yendon Stage 1

Follow the Yendon Stage 1 record through the 2021 monitoring attempts, the 26 October 2021 CRG report-status statement, the later 2022 monitoring campaign, the final SLR assessment, the attended-observation record and the frog-noise / rainfall comparison.

How to read technical documents

The reports should be read as a sequence

The technical record is not a set of isolated PDFs. Each document sits within a governing pathway that begins with the Planning Permit, passes through NZS 6808:2010 and the Noise Compliance Testing Plan, and then moves into background sound, post-construction assessment, auditor review, later technical response and disclosure records.

Original background monitoring

Marshall Day Acoustics Background Noise Monitoring Report

The original background monitoring report is published as a primary technical source because it records the first K15aa monitoring history and explains why later supplementary monitoring was undertaken.

Background Noise Monitoring Report

Date: 1 March 2018
Originating organisation: Marshall Day Acoustics
Document provenance: Primary technical report prepared for Lal Lal Wind Farms Pty Ltd as part of the pre-construction background noise assessment required under the Planning Permit.

Administrative significance

The report records that background noise survey and analysis was conducted in accordance with the Planning Permit and NZS 6808:2010. It records that K15aa was monitored during two separate surveys and that the data was affected by local extraneous noise.

The report further records that, for the second K15aa survey, the monitor was relocated to the only alternative position for placing the monitor in accordance with NZS 6808:2010, at a location representative of the noise environment around the dwelling.

Despite that relocation, the report concludes that the K15aa data was not suitable for deriving operational noise limits or assessing post-construction compliance.

Primary technical statement

“For the second survey, the noise monitor was relocated towards the front (eastern side) of the dwelling further away from the domestic air-conditioning system which was identified as the likely source of extraneous noise during the first survey. This location was identified as the only alternative position for placing the noise monitor in accordance with NZS 6808:2010, at a location representative of the noise environment around the dwelling.”

Documentary significance of the K15aa monitoring location

This report records that the original K15aa monitoring position was affected by local extraneous noise and that the monitor was relocated to the only alternative position identified as being in accordance with NZS 6808:2010 and representative of the noise environment around the dwelling.

Governing source wording

NZS 6808:2010 — Notional boundary: “A line 20 metres from any side of a dwelling or other building used for a noise sensitive activity, or the legal boundary where this is closer to such a building.”

Endorsed NCTP — measurement locations: “The following confirms the key aspects of NZS 6808:2010 with respect to measurement locations:
• The measurements shall not occur within 3.5 m of a vertical reflecting surface
• The measurements shall occur within 20 m of the dwelling.”

The subsequent SLR Baseline Noise Monitoring Report records that supplementary monitoring for K15aa was undertaken at a location approximately 100 metres from the dwelling.

Present documentary position

The record has not identified within the published record an accompanying instrument, approval or endorsed amendment authorising a departure from the measurement-location framework stated in NZS 6808:2010 and the endorsed NCTP. These documents are therefore presented together so readers can examine the documented monitoring locations and governing requirements in sequence.

Why this document forms part of the administrative record

This report establishes the original K15aa background sound monitoring record and explains why the subsequent supplementary baseline monitoring became significant within the Trustee's administrative and evidentiary record.

Contemporary operational record

Vestas Turbine Blade Incident Update

This operator-side update is included because it provides a dated record of turbine operation during September 2019, before the later Community Reference Group record and before publication of the SLR baseline report.

Blade incident, Yendon, Lal Lal Wind Farms

Date: 23 September 2019
Originating organisation: Vestas
Document provenance: Public incident update concerning the Yendon turbine-blade incident of 15 September 2019.

Administrative significance

The update records that Vestas temporarily suspended operation of all turbines at Lal Lal Wind Farm on 16 September 2019 following the blade incident. It further records that operation resumed later that day on all turbines except those in the Yendon section, which remained under inspection.

Why this record matters

The document is presented as a contemporary operational record relevant to the chronology of the 2019 K15aa supplementary monitoring. It is not relied upon here to determine the extent, duration or acoustic significance of turbine operation.

Community Reference Group record

Community Reference Group Minute — 1 October 2019

The 1 October 2019 Community Reference Group minute is included at this point in the chronology because it records the project status shortly after the September 2019 Vestas incident update and during the period later addressed in the SLR baseline report.

Project status recorded in the minute

Date: 1 October 2019
Document type: Community Reference Group minute

Administrative significance

The minute records that construction was complete and commissioning was ongoing. It is presented alongside the Vestas September 2019 operational update and the later SLR baseline report so readers can examine the 2019 chronology in the order the records were created.

Documentary sequence

The record does not treat the terms “operation”, “commissioning” and “operational commissioning” as interchangeable. The source documents are presented in date order so their respective wording can be read directly.

Supplementary baseline monitoring

SLR Supplementary Baseline Noise Monitoring Report

This report is published as a primary technical source because it records the supplementary K15aa baseline monitoring later relied upon throughout the administrative record.

Lal Lal Wind Farm Compliance — Baseline Noise Monitoring

Date: 16 February 2021
Originating organisation: SLR Consulting Australia Pty Ltd
Document provenance: Primary technical report subsequently incorporated into the Trustee's administrative and evidentiary record and repeatedly relied upon throughout that record.

Administrative significance

The report documents supplementary baseline monitoring undertaken during 2019 following the earlier Marshall Day monitoring. It records that the supplementary monitoring was undertaken to obtain valid baseline noise levels prior to the wind farm's operation and to determine operational noise limits.

The report states that the 2019 baseline monitoring campaigns at K15aa were conducted in accordance with the Planning Permit and NZS 6808:2010, as referenced in the Planning Permit. It also records Figure 2 showing the 2019 monitoring location and the two previous 2017 monitoring locations.

The report records that Batch 1 monitoring occurred between 31 July 2019 and 26 August 2019 without hub-height wind speed data, and that Batch 2 monitoring occurred between 22 October 2019 and 14 November 2019 using hub-height wind speed from the nearest energised WTG nacelle. The report states that no WTGs were operating during the Batch 2 period because it was prior to operational commissioning.

Primary technical statements

“This supplementary noise survey was conducted by SLR Consulting in 2019 to obtain valid baseline noise levels prior to the windfarm's operation and determine appropriate operational noise limits in accordance with the planning permit for the Lal Lal Wind Farm.”
“Baseline noise monitoring campaigns in 2019 have been conducted at receiver K15aa in accordance with the following: the planning permit for the Lal Lal Wind Farm; New Zealand Standard 6808:2010 Acoustics – Wind farm noise (NZS 6808:2010), as referenced in the planning permit.”

Why this document forms part of the administrative record

This report establishes the supplementary baseline methodology, monitoring location and background noise limits subsequently relied upon throughout the published technical record.

Auditor correspondence

ARUP EPA Auditor Letter

This correspondence is published as part of the primary technical source record because it records the auditor's explanation of verification issues and interpretation of relevant NZS 6808:2010 provisions.

EPA Auditor Correspondence

Date: 21 October 2022
Originating organisation: ARUP
Document provenance: Auditor correspondence concerning the Noise Management Plan and post-construction noise assessment verification.

Administrative significance

The correspondence forms part of the documented technical history because it records the EPA Auditor's explanation of post-construction verification, representative monitoring locations, revisions to technical reports and the interpretation of NZS 6808:2010.

Of particular significance, the Auditor expressly refers readers to section 2.1 (Terminology) of NZS 6808:2010, stating:

“I note that S2.1 of NZS6808:2010 states; ‘For the purposes of this Standard, the word ‘shall’ refers to requirements that are mandatory for compliance with this Standard, while the word ‘should’ refers to practices that are advised or recommended.’”

The correspondence then applies that interpretive distinction when discussing supplementary background noise measurements, representative monitoring locations and post-construction assessment.

Why this document forms part of the administrative record

This correspondence provides the auditor's explanation of technical verification issues and therefore sits between the SLR technical correspondence and the later Appendix H re-analysis within the chronological technical record.

Technical correspondence

SLR Technical Response Letter

This correspondence is published as part of the primary technical source record because it records SLR's explanation of the relationship between pre-construction assessment, the K15aa reference receptor, interim monitoring during early operation and the Stage 1 compliance assessment.

Elaine Wind Farm — Noise Compliance

Date: 1 December 2022
Originating organisation: SLR Consulting Australia Pty Ltd
Document provenance: Technical correspondence prepared by SLR Consulting concerning pre-construction assessment, operational monitoring and compliance assessment for the Lal Lal Wind Farm.

Administrative significance

Documentary reading note: The SLR Technical Response Letter states that “Pre-construction baseline noise monitoring was completed by SLR at location K15aa in approximately October 2018 and the relevant noise limits determined.” The published SLR Baseline Noise Monitoring Report, dated 16 February 2021, records supplementary monitoring undertaken during 2019, including Batch 1 from 31 July to 26 August 2019 and Batch 2 from 22 October to 14 November 2019. NZS 6808:2010 defines “Background sound” as “The A-frequency-weighted L90 centile level measured prior to the installation of any wind turbines in an area.” The endorsed NCTP provides: “Prior to commencement of operation of the wind farm, an updated background noise report is to be submitted to the responsible authority, detailing the monitoring results for K15aa.” The Community Reference Group minutes of 1 October 2019 record that construction was complete and commissioning was ongoing. SLR Appendix H later revisited the 2019 K15aa dataset after identifying early commissioning during part of the monitoring period. The record reproduces these dates, descriptions and requirements from the source documents so readers can examine how the published record fits together.

The correspondence forms part of the published technical record because it explains the relationship between the pre-construction background noise assessment, the reference receptor adopted for compliance assessment, interim operational monitoring and the subsequent Stage 1 compliance assessment.

The correspondence records that pre-construction baseline noise monitoring was completed by SLR at location K15aa in approximately October 2018 and the relevant noise limits were determined; that the Pre-Construction Noise Assessment predictions of wind farm noise formed part of the assessment chronology; that K15aa was repeatedly identified as the relevant reference receptor for J14aa; and that SLR referred to complaints-based interim compliance monitoring undertaken during early wind farm operation.

Primary technical statements

“Pre-construction baseline noise monitoring was completed by SLR at location K15aa in approximately October 2018 and the relevant noise limits determined.”
“The reference receptor K15aa is nearest to J14aa (~2.3km).”
“The complaints based interim compliance monitoring result during early wind farm operation…”

Why this document forms part of the administrative record

This correspondence documents SLR's explanation of how the K15aa baseline monitoring, pre-construction assessment, reference receptor methodology and subsequent operational compliance assessments were intended to operate within the technical framework established by the Planning Permit, the approved NCTP and NZS 6808:2010.

Subsequent technical review

SLR Appendix H — K15aa Baseline Re-analysis

Appendix H is published as a primary technical source because it revisits the same supplementary K15aa baseline monitoring after identifying that aspects of early commissioning had occurred during part of the 2019 monitoring period.

Appendix H — Receptor K15aa Baseline Re-analysis

Date: 20 September 2024
Originating organisation: SLR Consulting Australia Pty Ltd
Document provenance: Technical appendix relied upon throughout Annex A and the Supporting Record and Analytical Memoranda.

Administrative significance

Appendix H forms part of the published technical chronology because it revisits the K15aa supplementary baseline monitoring dataset that had previously been described as pre-construction baseline monitoring.

The earlier SLR Technical Response Letter dated 1 December 2022 states that “Pre-construction baseline noise monitoring was completed by SLR at location K15aa in approximately October 2018 and the relevant noise limits determined.” The published SLR Baseline Noise Monitoring Report dated 16 February 2021 records supplementary baseline monitoring undertaken during 2019 and states: “No WTGs operating during Batch 2.”

Governing source wording

NZS 6808:2010 — Background sound: “The A-frequency-weighted L90 centile level measured prior to the installation of any wind turbines in an area.”

Endorsed NCTP — K15aa requirement: “Prior to commencement of operation of the wind farm, an updated background noise report is to be submitted to the responsible authority, detailing the monitoring results for K15aa.”

Appendix H then records SLR's subsequent re-analysis of the same 2019 supplementary monitoring dataset after identifying that aspects of early commissioning had occurred during part of that monitoring period. The appendix documents SLR's assessment of whether operational turbine noise influenced the K15aa baseline dataset and presents revised analytical outputs.

How this record should be read

Accordingly, Appendix H should be read together with the SLR Technical Response Letter, the SLR Baseline Noise Monitoring Report, NZS 6808:2010, the endorsed NCTP and the Community Reference Group minutes of 1 October 2019 so readers can examine the complete documentary chronology.

Why this document forms part of the administrative record

This document is the later technical review that completes the published chronology from original background monitoring, through supplementary baseline monitoring, technical correspondence and auditor correspondence, to subsequent re-analysis.

Public technical information session

Contemporary public explanation of the methodology

Following completion of the Stage One post-construction noise assessment, SLR Consulting conducted a publicly available online information session explaining the methodology adopted for the assessment and the technical framework governing operational noise compliance.

Watch the public information session

The presentation discusses the Planning Permit framework, the NCTP, NZS 6808:2010, pre-construction baseline and post-construction monitoring methodology, attended listening observations, extraneous environmental noise, special audible characteristic assessment and environmental auditor verification.

Preservation notice: This page links to the official YouTube publication while it remains publicly available. For continuity of the documentary record, the Trustee has retained an archival recording of the publicly available livestream as originally published. The preservation copy is not intended to replace the official source and will only be made available if the original publication becomes unavailable.

Transcript notice

The accompanying transcript was downloaded from the publicly available YouTube recording. It has not been edited or corrected by the Trustee and may contain automated transcription errors, including inaccuracies in punctuation, technical terminology, names or acronyms.

It is provided solely as a reader aid. Where any discrepancy exists, the video recording should be regarded as the authoritative source.

Historical reconstruction

Operational Timeline — 31 March 2021

This figure is published beneath the public information session and transcript because it relates to the Q&A discussion concerning the Stage 1 Elaine attended observations, daylight saving time and whether the wind turbines were operating during the recorded observation periods.

Operational Timeline — 31 March 2021

Document type: Historical reconstruction / analytical exhibit
Prepared by: Beneficiary
Document provenance: Historical documentary record assembled by the Beneficiary prior to establishment of the Trustee's continuing administrative record.

The figure was prepared as a historical reconstruction using publicly available AEMO generation data, the attended observation times recorded in Appendix D of the Stage 1 Elaine Post-construction Noise Assessment, and contemporaneous documentary material then available.

Following execution of the Owen Robert Inter Vivos Trust, the Trustee incorporated the figure into the continuing administrative record as historical reference material. It is published to assist readers in understanding the chronology of the attended observations discussed during the public SLR Information Session, including Question 1 (Part B) raised by the Beneficiary. At approximately 53:53 of the Information Session, SLR's Technical Director addressed the relationship between the attended listening observations, the AEMO generation data and the applicable time reference, including an explanation concerning Australian daylight saving time.

Information Session — Question 1 (Part B), commencing at 53:53

SLR's Technical Director stated:

“I just will hasten that you can't really make any conclusions based between the survey times or strictly make any conclusions around the survey times. There almost certainly is a discrepancy in the time datum used. Our survey times being in March would have been with Australian daylight savings time and I suspect you'll find the AEMO times are probably just Australian Eastern Standard Time, so they don't have to deal with daylight saving, so there's probably an hour out difference. So I guess there's no conspiracy there. It's likely that it was in one of the periods when it was operating, albeit at a low level.”

Operational timeline reconstruction for 31 March 2021 showing wind energy production and attended observation times
Primary source documents

Technical document library

These links preserve the existing document access while placing the technical reports into the new learning pathway.

Original 2018 background monitoring report and K15aa monitoring history.
PDF
Supplementary K15aa baseline monitoring report dated 16 February 2021.
PDF
Technical correspondence concerning K15aa, J14aa, pre-construction assessment and early operation.
PDF
Auditor correspondence concerning verification issues and NZS 6808 wording.
PDF
Later technical re-analysis of the K15aa baseline monitoring record.
PDF
Reader aid transcript of the public information session. The video remains the authoritative source.
PDF
Record note: The purpose of this page is to present the published technical record in chronological order and connect it to the Glossary, Framework and evidence pages. Where successive documents discuss the same technical issue, they are presented sequentially so readers may understand the evolution of the record using the original source documents.
Later agency reliance

Where agencies enter the technical record

Technical reports should also be read with the later agency correspondence and Freedom of Information record. The Agency Records gateway identifies where EPA Victoria, DTP, Moorabool Shire Council and the AEIC referred to, relied upon, received or disclosed technical material within the currently published record.

Published Sonus assessment

June 2018 Sonus S5464C11

The report released under DTP FOI CS015466 is now available in full. A dedicated documentary guide separates the planning-stage prediction, formal post-construction assessment pathway, later correspondence and EPA reliance record.

Sonus documentary update

ARUP verification comparison

The three published ARUP verification statements consistently identify the Marshall Day predictive assessment dated 17 January 2018. Highlighted extracts and complete reports are now available in the Sonus documentary guide.

Operational management pathway

Noise Management Plan

The October 2022 NMP is read alongside the endorsed NCTP, the receiver-location framework, background-noise reports, EPA correspondence, auditor-verification requirements and the FOI custody record.